I had detected some Stage 9 issues with my system last week using 6.3.0 pro. I switched over to 7b1 because there was mention of some updates to ECC testing and the Atom c2000 chipset (I'm using the C2750).
I made the following test changes:
Only test 9, and then a small range. Number of test passes set to the max I could: 999. After running for a short while and not detecting anything, I "reset" the range, re-enabled all tests and re-ran things.
I came in this morning, and it showed "completed" however, only with 140 passes. It also didn't detect any further issues with the memory.
Is the system hard-coded to stop at 140 passes?
I'm going to re-run the same test with the older 6.3.0 pro iso to see if I get similar results.
I made the following test changes:
Only test 9, and then a small range. Number of test passes set to the max I could: 999. After running for a short while and not detecting anything, I "reset" the range, re-enabled all tests and re-ran things.
I came in this morning, and it showed "completed" however, only with 140 passes. It also didn't detect any further issues with the memory.
Is the system hard-coded to stop at 140 passes?
I'm going to re-run the same test with the older 6.3.0 pro iso to see if I get similar results.
Comment